Notification of 2027 Road Work Project

2027 Road Construction Project

Greetings,

            This letter is to inform you of upcoming road work that will affect your neighborhood in the Town of River Falls.

Starting in April of 2027 the Town of River Falls will be doing a complete rebuild of portions of 850th Street south of State Road 29 to the intersection with 830th Avenue, then the project will go east of 850th Street on 830th Avenue to the top of the hill approximately 5,300 feet. The project next year is approximately 6,800 feet in total length or about 1.3 miles. The project cost is estimated to be about $750,000.00 in total. Most of the work will be completed by our 2 Town employees. The scope of work will involve the following:

 

Phase 1, in mid to late April the existing blacktop surface will be pulverized (ground up) into pieces approximately 6” and smaller. Residents will be driving on the pulverized road for a short while until the old material is removed. This will be rough so speeds will be reduced to 25mph during the full road reconstruction period. 25 is advisory maximum, slower speeds may be necessary for safe driving. The use of alternate routes is advised during the entire construction period.

 

Phase 2, all the old blacktop, crushed rock and road base will be removed where necessary, this is expected to take a minimum of 3 weeks to complete, the road will stay open to local traffic during that time but there will be delays as the road will be down to one lane during the removal process, residents will have wait times as equipment is filling or dumping loads. The old base material will be placed along the edge of the road in areas where steep slopes are, this will create better side slopes. The existing black dirt will be removed so the old road material can be placed making the roadway safer for future use. We have already met with a few property owners where fences need to be moved before construction. Black dirt will be bladed back from the road edge for the entire project length during phase 2. The road surface during phases 2 and 3 can change hourly, extreme caution should be taken anytime a resident is driving in a construction zone.

 

Phase 3 will involve placing a new road base before the new layer of blacktop is installed. The new base will consist of approximately 12” of compacted crushed rock 6” in diameter and less, then that material will be covered with 10” of compacted ¾” crushed limestone. The base will be installed 26’ in total width with the blacktop surface being 22’ in width, the 2-foot difference on each side will give edge support to the new

 

blacktop, this will prevent edges from cracking and breaking. The estimated total loads of material being delivered is 640 truckloads, Truck traffic will be very heavy during this period of the project. Phase 3 is expected to take 3-4 weeks. If all goes well phase 3 will be completed by early to mid-July.

 

Phase 4 will be blacktopping the road surface. Blacktopping will not occur until late September or October. The Town does not immediately blacktop the road after the new base courses are installed, delaying the blacktopping gives the Town a couple months to monitor the new base to make sure there are no soft spots in the base.

 

Phase 5 will involve putting in new gravel shoulders after blacktopping, these will be 24” in width on both sides of the road. After that, the final shaping and spreading of the black dirt in the ditches occurs. If a resident has been mowing the road right of way, the Town does not do final seeding to what a weekly maintained lawn is. The Town picks rocks down to about a 5” diameter and does a rough final grade. The Town mows at a height higher than 6” when mowing ditches, if a resident decides to maintain the road right of way in front of their property at a higher level, the resident will be responsible for grading and seeding the ditch to the higher standard. Depending on fall weather the amount of growth will vary every season, some reseeding in the spring may occur. New signage will be installed during the final phase.

 

Any questions or concerns please contact Terry Kusilek, Town Chair @ [email protected] or by cell @ 715-821-4049, no texting to this number.